Project Details
Umniah PV Power Plant covers the need of Umniah Telecommunication Company. The total project capacity was 17.75MWp
distributed along with four sites. Three of them are located in Almafraq Governate circumference (Dhulail, Halabat, and Khaldeye). The fourth was in Al-Azraq. SAMT took the Construction of both Electrical and Mechanical works along with Testing and Commissioning. The completion date was October 2019 and delivered to Belectric Gulf; SAMT’s Client
Project Name
Umniah
Project Size
17.75 MWp
Project Location
Jordan
Client Name
Belectric Gulf
Scope Of Work
Construction of electrical and mechanical works, Testing & Commissioning